Payment

What is retention, and how do you actually get it released?

6 min readUpdated 27 July 2026

The short answer

Retention is a percentage of each payment that the paying party holds back as security that you’ll finish the work and put right any defects. No statute sets the rate. It’s whatever the contract says, and in UK construction it’s commonly 3% to 5% of the value of work done. It’s normally released in two halves: the first at practical completion, and the second at the end of the rectification or defects liability period, usually six or twelve months later. The money stays yours throughout. Retention is a deduction from a payment, not a reduction in the contract sum.

At a glance

Typical rate
3% – 5%
Usual cap
Half the rate after PC
First release
Practical completion
Second release
End of rectification period
Rectification period
Commonly 6 or 12 months
Statutory cap
None
Large-firm reporting
Financial years from 1 April 2025

How is retention calculated?

As a percentage of the gross valuation on each payment application, deducted before the previously paid amount comes off. On a £100,000 valuation with 5% retention, £5,000 is held and £95,000 is certified, less whatever you’ve already been paid.

Most contracts also cap the total retention held, often at 3% of the contract sum, so it stops accruing once the cap is reached. Most halve the percentage at practical completion too, so the first release is usually half of what’s being held.

StageRetention heldOn a £500,000 contract at 5%
During the worksFull rate, up to any cap£25,000
At practical completionHalved£12,500 released, £12,500 held
End of rectification periodNil, once defects are made good£12,500 released

Retention is a deduction from payment, not a reduction of the contract sum. It stays your money.

Why is retention so hard to recover?

Because by the time it falls due, everyone who cared about the job has moved on. The site team is elsewhere, the quantity surveyor has a new project, and the sum is small enough against the contract value that nobody upstream is chasing it. Retention isn’t usually withheld out of malice. It’s forgotten.

The recurring causes, in roughly the order they cost money:

  • Nobody recorded the practical completion date, so nobody knows when the release fell due.
  • The rectification period end date was never diarised.
  • The retention was netted off inside a valuation and never appeared as a line anyone could see.
  • The main contractor is holding it against your client’s retention and can’t release until it’s released to them.
  • There’s a defects list nobody closed out, so the second release never becomes payable.
  • The paying company went insolvent, and retention held in its general account is an unsecured debt.

NoteThat last one is the real risk. Unless the contract requires retention to be held in a separate trust account, you’re an unsecured creditor for it. Ask for a trust account at contract stage; nobody grants one after the event.

How do you get retention released?

  1. 01Record the two dates on day one. Practical completion and the end of the rectification period. If PC hasn’t happened yet, record the target date and update it.
  2. 02Get practical completion certified in writing. A certificate, or at minimum an email from the contract administrator confirming the date. Verbal PC isn’t a date you can enforce against.
  3. 03Close the defects list. Photograph each item as it’s completed and send the evidence at the time, not in a bundle at the end. An open snag is the standard reason for withholding the second half.
  4. 04Apply for it formally. Retention release is a payment like any other. Make it an application or an invoice under the contract mechanism, with the sum and the basis stated, so the payer has to serve a pay less notice to withhold it.
  5. 05Diarise the chase. Seven days after the final date for payment, then escalate to the commercial contact rather than the site contact.
  6. 06Use the leverage the Act gives you. A retention release application that goes unanswered becomes a notified sum, and an unpaid notified sum can be referred to adjudication. Adjudication is quick, and available at any time.

Apply for retention release under the contract payment mechanism. It then carries the same notice regime as any other application, and the payer has to serve a pay less notice to withhold it.

What did the 2025 reporting rules change?

The Reporting on Payment Practices and Performance (Amendment) Regulations 2025 came into force on 1 March 2025 and apply to financial years beginning on or after 1 April 2025. They extend the existing large-company payment reporting duty to retention held under construction contracts.

Qualifying companies and LLPs now have to publish, twice a year:

  • Whether their construction contracts include retention clauses
  • The standard retention percentage they apply
  • The contract value threshold below which they do not take retention
  • The procedure they follow for releasing retention

That doesn’t force anyone to release your retention. What it does do is put the policy on a public register, and that helps at tender stage. You can look up a main contractor’s stated retention practice before you price their work, then quote it back at them when the release runs late.

NoteThe duty falls on large businesses only: broadly those exceeding two of the three thresholds for turnover, balance sheet total and employees. Most subcontractors are reading these reports, not filing them.

Should you accept retention at all?

On public and large private work, refusing usually isn’t an option. On smaller commercial work it often is. Ask about the alternatives: a retention bond, a parent company guarantee, or simply a lower rate. Retention on a £20,000 subcontract is security worth £600 to the payer and administration worth more than that to both of you.

If you do accept it, price it. Retention held for eighteen months is a real financing cost, and a firm carrying £40,000 of retention year-round is funding it out of the overdraft. That belongs in your overhead recovery; it shouldn’t come out of your margin by accident.

How does Estimark track retention?

Retention is deducted on the payment application and tracked to release, with retention releases raised as invoices carrying the same VAT treatment as any other invoice, reverse charge included. Payment Applications is a module of its own at £19 a month, bundled from Pro upward.

Being straight about the limits: Estimark doesn’t chase retention for you, doesn’t send a reminder when a rectification period is about to end, and doesn’t hold retention in trust. It keeps the figure visible and attached to the job, so the release is a task rather than an archaeology dig. See payment applications and retention.

Questions

Frequently asked

What is a normal retention percentage in UK construction?

Commonly 3% to 5% of the value of work done, often capped at around 3% of the contract sum, and usually halved at practical completion. There’s no statutory rate; it’s whatever the contract you signed says.

When should retention be released?

In two stages under most standard forms: half at practical completion, and the balance at the end of the rectification or defects liability period, which is commonly six or twelve months after practical completion and conditional on defects being made good.

Is there a legal limit on how much retention can be held?

No. There’s no statutory cap on the percentage or on how long it can be held. The Construction Act governs the notices and timing of payments, including retention releases, but not the rate itself.

What happens to my retention if the main contractor goes bust?

Unless the contract requires it to be held in a separate trust account, retention sits in the contractor’s general funds and you rank as an unsecured creditor for it. So negotiate a retention bond or a trust account at contract stage. Nobody agrees to one after practical completion.

Can I adjudicate to recover retention?

Yes, where the Construction Act applies. Retention release is a payment under the contract, so an application for it that receives no payment notice and no valid pay less notice becomes a notified sum, and non-payment of a notified sum can be referred to adjudication at any time.

Build on a solid foundation.

Run the whole business without an implementation project and without legacy baggage. Every plan starts with 14 days free.

Estimating · Jobs · Invoicing · CIS · H&S · Reactive maintenance