Pricing

How to price a job properly: labour, materials, plant and overhead

7 min readUpdated 27 July 2026

The short answer

Price a construction job from the bottom up, in this order: labour at its true cost including employer’s National Insurance, holiday and non-productive time; materials at current merchant prices plus a waste allowance; plant and equipment; preliminaries and site costs; a share of your annual overhead; and then margin on top of the lot. The single most common error is treating an hourly charge-out rate as if it were the cost of an hour’s labour. If a job is priced at cost plus 20% but overhead was never in the cost, that 20% isn’t profit. It’s the contribution towards running the business, and there’s nothing left after it.

At a glance

Employer NI (2026/27)
15% above £5,000 a year
Statutory holiday
5.6 weeks, capped at 28 days
Holiday accrual, casual
12.07% of hours worked
Typical waste allowance
5% – 10%
CITB levy (2026–29)
0.35% PAYE, 1.25% net CIS
CITB exemption below
£150,000
Order of operations
Cost, then overhead, then margin

What does an hour of labour actually cost?

Far more than the wage. Take an employed carpenter on £22 an hour and work out what the business pays for each hour they’re actually productive on site.

  • Gross pay. £22 an hour, with holiday pay on top of worked hours. The statutory minimum is 5.6 weeks, capped at 28 days for a five-day week. For irregular-hours and part-year workers, accrual at 12.07% of hours worked is the standard method.
  • Employer’s National Insurance. 15% on earnings above the £5,000 secondary threshold in 2026/27, subject to the Employment Allowance where you qualify.
  • Pension. Auto-enrolment minimum employer contribution of 3% of qualifying earnings.
  • Non-productive time. Travel between sites, loading, merchant runs, training, toolbox talks, sick leave, waiting for other trades. This is normally the biggest adjustment of the lot.
  • Training, PPE, tools and certification. CSCS renewals, IPAF, PASMA, first aid, and the annual replacement of hand tools.
  • Employer’s liability insurance, which is compulsory, and public liability.
  • The CITB levy where you’re in scope. The 2026–29 proposals keep the rates at 0.35% of PAYE and 1.25% of net paid taxable CIS subcontractor payments, with no levy below £150,000 of combined payroll and CIS payments, and a 50% reduction up to £500,000.

Productive hours, not paid hours, are what you divide by. An operative paid for 2,000 hours a year who is productive for 1,600 costs 25% more per productive hour than the payroll suggests.

Work out your own number once a year from real payroll data, and use it. A charge-out rate copied from what the firm down the road charges isn’t a costing method.

How should materials be priced?

  1. 01Take off quantities from the drawings or a measured survey. Don’t eyeball it.
  2. 02Get current prices, not last quarter’s. Ask the merchant to hold the price for the quote validity period.
  3. 03Add a waste allowance. Typically 5% for boarding and sheet goods, up to 10% for tiling, cut timber and blockwork, and more where the geometry is awkward.
  4. 04Add delivery, and skip or waste transfer costs. Those need a waste transfer note in any case.
  5. 05Add a percentage for handling and storage if you are buying the materials rather than the client.
  6. 06Decide the mark-up separately from your margin, and be explicit about it.

NoteWhere CIS applies to a subcontract, the direct cost of materials is excluded from the deduction base. That’s a tax calculation, not a pricing one. See how CIS deductions are calculated.

What about plant, preliminaries and site costs?

Plant is straightforward if you hire: the hire rate, delivery and collection, fuel, and the idle days at weekends when it’s on site but not working. If you own it, use an internal hire rate that recovers purchase, servicing, LOLER thorough examination and eventual replacement. Owned plant isn’t free.

Preliminaries are the costs of running the site rather than doing the work, and on small jobs they’re almost always underpriced, because they’re invisible.

  • Site set-up, welfare facilities and security, all required under CDM 2015 regardless of size
  • Scaffolding, temporary works and access equipment
  • Supervision and site management time
  • Skips, waste transfer and cleaning down
  • Parking, permits, congestion or clean air charges
  • Temporary power and water
  • Protection of finished work and existing surfaces
  • Contract-specific insurance and any bond or warranty requirement

Two days of supervision on a two-week job is 20% of a working fortnight. If it isn’t in the price, it’s out of your margin.

How do you recover overhead?

Overhead is everything the business costs that can’t be pinned to a single job: office rent, vehicles, accountancy, software, insurance, marketing, the estimator’s time, the phone bill, the director’s salary. It has to be recovered across the jobs you win. You can’t do that without knowing the annual number.

  1. 01Total your annual overhead from last year’s accounts, adjusted for what you know has changed.
  2. 02Total your expected productive labour hours for the year across the whole business.
  3. 03Divide. That’s your overhead recovery per productive hour.
  4. 04Add it to every hour you price, on every job.

A firm with £96,000 of annual overhead and 4,800 productive hours has to recover £20 for every productive hour it sells. Not roughly, and not on the big jobs only. Win less work than you planned and the recovery per hour rises, so a quiet year is dangerous even when every individual job looked profitable.

Margin is what’s left after overhead has been recovered. If overhead was never in the cost, your margin is your overhead.

Can you show me a worked example?

A ten-day refurbishment, two operatives, using illustrative figures.

ElementCalculationAmount
Labour2 operatives × 8h × 10 days × £34/h true cost£5,440
MaterialsTake-off £3,200 + 7.5% waste£3,440
Plant hireTower and floor saw, 10 days£420
PreliminariesSkips, welfare, protection, parking£680
Supervision1.5 days at £46/h true cost£552
Total cost£10,532
Overhead recovery160 productive hours × £20£3,200
Cost plus overhead£13,732
Margin at 15%£2,060
Price£15,792

The instructive line is the overhead. A firm pricing the same job at cost plus 20% would quote £12,638, nearly £3,200 less, and would call it a profitable job while making an actual loss of about £1,100 once the year’s overhead is allocated. That’s how busy firms go under.

NoteDon’t confuse margin with mark-up. A 15% margin on a £15,792 price is £2,369 of the price; a 15% mark-up on £13,732 of cost is £2,060. Pick one convention and state it in your own paperwork.

What else belongs in the price?

  • Risk. Unknown ground, an occupied building, a listed structure, a client with a history of changing their mind. Price it as a contingency line or decline the risk explicitly in the exclusions.
  • Retention. Money held for up to eighteen months has a financing cost. See retention and how to get it released.
  • Payment terms. Sixty-day terms on a job you fund up front are a real cost. Price them or negotiate them.
  • Liquidated damages, where the contract has them, and whether the programme is achievable.
  • Inflation, on anything with a long lead-in or a fixed price over more than a few months.
  • Warranty and defects liability obligations you are taking on after completion.

And write the exclusions down. Most disputes about price are really disputes about scope, and a quote that lists what isn’t included is worth more than one that only lists what is.

How does Estimark help with pricing?

Estimating and quoting with line items, quantities and VAT are on every plan, starting at £39 a month. Quotes convert to jobs, so the price you quoted and the job you deliver are the same record.

The part that closes the loop is job costing. The Job Costing module, £25 a month on its own and bundled from Core upward, builds a live cost position for each job from the cost ledger, timesheet hours and purchase orders as they’re receipted, splits it across labour, materials, plant, subcontractors and the rest, and reconciles it against certified value. It’s what tells you whether the £34 an hour you priced at is the £34 an hour you’re actually paying.

What Estimark doesn’t do is calculate your overhead recovery rate or set your labour rate. Those come from your accounts. See job costing and CVR and Estimark for builders and contractors.

Questions

Frequently asked

What is a reasonable profit margin for a construction job?

There’s no single right answer, and published industry margins vary widely by sector and size. What matters more is that overhead is recovered before margin is added. A 10% margin on a price that fully recovers overhead is worth more than a 25% margin on a price that doesn’t.

How do I work out my labour rate?

Take the total annual cost of employing someone: gross pay, holiday, employer’s National Insurance at 15% above the £5,000 secondary threshold, pension, training, PPE, insurance and any CITB levy. Divide that by the hours they’re actually productive on site, not the hours they’re paid for. The gap is usually 15% to 25%.

What waste allowance should I add to materials?

Commonly 5% for boarding and sheet materials and up to 10% for tiling, cut timber and blockwork, with more where the geometry is awkward or the material is fragile. Use your own historical waste figures where you have them; they’re more accurate than any rule of thumb.

Margin and mark-up: what’s the difference?

Mark-up is a percentage added to cost. Margin is a percentage of the selling price. They aren’t the same number: a 25% mark-up on £100 of cost gives a £125 price and a 20% margin. Confusing them consistently under-prices work, so pick one convention and use it everywhere.

Should I show a breakdown on the quote?

Show enough to make the scope unambiguous: the elements of work, what’s included, what’s excluded. Don’t expose your labour rate and overhead recovery to a client who’ll negotiate them line by line. Be generous with the exclusions.

Build on a solid foundation.

Run the whole business without an implementation project and without legacy baggage. Every plan starts with 14 days free.

Estimating · Jobs · Invoicing · CIS · H&S · Reactive maintenance